Sunshine Acres Property Owners
Association.
January 22, 2005 Semi-Annual Meeting Minutes
Meeting called to order at 1:05 p.m. by SAPOA President Dave Taney.
The January 8, 2005 was canceled due to snow and rescheduled for today
by
sign board, January 22nd.
A quorum was established with 50 property owners, including 6 Board
members.
Past Meeting Minutes:
The July 10, 2004 Semi-annual Meeting minutes were handed out and a
motion
to accept them as presented was made by Jim Martin and seconded by H.L.
Font.
The motion passed unanimously.
Treasurer’s Report:
Irma Martin’s report is in two parts and on a handout. The first part
opens
with August 31, 2004 at $15,759.82 Income was $2,351.62, with a balance
of
$18,111.44. Part two ending balance is $40,077.15. A
motion
was made to accept the report as given and H.L. Font seconded the
motion.
The motion was passed.
Dues:
There are 402 property owners. 2004-2005; $4,130 dues are outstanding.
2004-2005 Financial Records Audit:
Jeanette Clark audited the books finding one minor discrepancy, which
had
to do with when a check was entered and when that check was mailed.
Copies
of Ms. Clark’s audit were available at the meeting.
Mussel Beach Road Lease:
Everett Stauffer reports DNR paperwork is done and an April payment
will
be required. Shoreline survey must be done within 5 years. Mr. Stauffer
will
check if SAPOA can go in conjunction with Diamond Point.
Mussel Beach Road Committee Report:
The following is a copy of BRC report presented by Sam Mrakovich at
meeting.
Beach Road Report to the SAPOA Membership
January 22, 2005 Membership Meeting
The Beach Road Committee (BRC) is very pleased to
report
at today’s meeting that the first phase of the Beach Road maintenance
project
is ongoing and about 60% complete. This phase installs the drainage
system
and prepares the road for paving, leaving the road in a drivable
condition
until it is paved. All work to date and all work planned, including
miscellaneous
property improvements, remains well within the 3-year funding
commitment
made by the membership when you approved the ballot request in
September
2004.
The Beach Road Committee has made difficult
decisions.
Getting to where we are today has not been without challenges. The
project
was started before all dues for this phase were received. There are
members
who have yet to pay last fall’s dues, which are needed to pay for this
phase.
At the onset, the contractor hit a sewer line that was not in county or
SAPOA
records. The sewer line was relocated at our (Beach Road account)
expense.
A retaining wall was needed to stabilize the high bank at the old slide
area.
It was deemed necessary before the culverts were installed. Both of
these
items incurred a surprise expense. The need for the wall was identified
soon
after the last general meeting by the BRC. Cost negotiations with the
contractor
had been completed. As a result of a misunderstanding by the
contractor,
this very necessary retaining wall got a jump-start one day before a
means
of paying for it could be formulated. Remember, although the membership
funding
for the total project is adequate, the once-a-year deposit into the
Beach
Road account creates cash flow problems. A project of this size is
going
to have unexpected occurrences along the way and must somehow be kept
going
to avoid increasing overall cost.
Financial Decisions
For all known expenses to date, there is a shortfall until next fall’s
dues
are received. This shortfall results from the unpaid 2004-05 dues, the
unexpected
sewer line relocation, and the retaining wall installation. The
shortfall
sum total comes to approximately $18,000.
That brings us to the primary purpose for this meeting which is
membership
approval for the BRC’s proposed solution that follows or an alternative
solution
proposed by the membership that will allow the successful completion of
the
total project within the 3-year funding totaling approximately $90,000.
At
this point, the paving cost is only a rough estimate of about $50,000.
The proposed solution by the BRC is as follows:
1. Accept the contractor’s offer to finance any
unpaid
project cost at a simple interest rate of 7.25% APR, to be
calculated
daily (not compounded) against the maximum balance for that day. There
would
be no monthly payment requirement for one year maximum at which time
the
full principal amount and accumulated interest charges would be due. No
pre-payment
penalties would be imposed for partial or complete principal payoff.
The financed amount will be less than $20,000 considering all project
expenses
that have been identified and are expected for this phase of the
project.
At least $30,000 in Beach Road funds will flow into the Beach Road
account
each fall for the next 3 years. Payoff of the account balance
should
occur next fall if not sooner. Finance charges for $18,000 for 6
months
(if no pay down of principal) would be $652.50. This offer by the
contractor
is contingent upon approval of Item 3 below.
2. The membership would be encouraged to make advance
payments
of the Beach Road portion ($75 per year) of the next 3-year’s dues
obligation.
This advanced income for the Beach Road account would improve the cash
flow
and be used to reduce or eliminate the financed shortfall.
3. The retaining wall cost would be paid from the
Beach
Road account as any other completed expense item. Financing would
begin
upon depletion of the Beach Road account and pay down of the principal
would
occur as Beach Road dues are received.
This 3
part
solution will allow the first phase of the project to be completed
without
interruption. Accepting this small finance cost now will save
several
times more in added expenses if construction had to stop until the
September
2005 funding is received.
The Beach Road Committee
The Beach Road project underway is the biggest
project
SAPOA has ever undertaken and most likely the biggest it will ever
undertake.
It is being managed by the Beach Road Committee (BRC) with oversight by
the
SAPOA Board of Directors, who write the checks. The Committee,
comprised
of 10 members, was formalized in two ways shortly after the July 2004
annual
meeting. First the 10 current members were decided upon and approved at
a
SAPOA Board Meeting. At a later Board meeting, the following functions
and
responsibilities for the BRC were approved by the SAPOA Board:
“ 1. That, as an ongoing function, the BRC monitors
the
Beach Road property and apprises the
SAPOA
Board
of its condition and recommends necessary maintenance or closure to
protect it
from
deterioration as a special amenity for SAPOA members. The Beach Road
is
considered
to be both the roadway and the adjoining drainage system.
2. That, as directed by the SAPOA Board for special
projects,
in full compliance with Article VII, Section 5, paragraph h, the BRC
shall
act as facilitator and advisor to the SAPOA Board regarding actions
required
to successfully accomplish these projects.
In all cases of maintenance of the Beach Road property, the BRC shall
determine
what
maintenance will be required, the costs, and the timetable for
implementation.”
The current BRC is comprised of the following volunteer property owners:
Vince Convery Sam Mrakovich,
Chairman
Diana Davidson Barry Olson
Nancy Drake Steve Ramsey
Cecilia Eckerson Larry Werner
H. L. Font Bob Zuehlsdorff
The BRC thanks you for attending this meeting. (End of report.)
Mr. Mrakovich reiterated what the membership voted on before work began
on
the road and that Mr. Taney has been active in attending Mussel Beach
Committee
meetings in the planning process, including deciding on the contractor.
The
engineered plans that SAPOA paid for in 2001 have proven to be a
challenge
to work with on several points. The design engineer has been involved
with
the present committee, redlining the initial plans as the project
progresses.
Mr. Mrakovich talked about how dedicated each member of the BRC has
been
and still is. The members being approved by the Board last fall, are
diverse
and independent thinkers. Of course, being property owners and anxious
to
use the launch ramp, they have an interest in getting the project
completed.
They are conscientious and knowledgeable. It is important that, if
property
owners who care about the road have questions, in all fairness to
contact
the members of the committee as well as the Board. Barry Olson has many
years
experience with stabilizing banks. Steve Ramsey has been the foreman,
communicating
with the contractor and committee. The BRC has been involved with many
meetings:
3 in July, 5 in August, and 3 in September, October, November. The
contractor
we chose and the Board approved had some innovative ideas that made
sense.
He is conscientious and patient, especially in waiting for materials to
work
with. Juniper Avenue is a problem as far as water entering the slide
area.
The retaining wall was installed in order to stop any slides from
happening
now and especially over the culvert which is being installed. The
retaining
wall has been a part of the plan and was discussed with the BRC and
Board
in August. Again, Barry Olson’s expertise was instrumental in figuring
out
a viable stable wall and how it was to be done. Mr. Olson’s plan saved
us
money from the initial plan. The wall was “prematurely” put in
according
to contract, although it is timely according to need. The problem lies
in
the cash flow and payment of the retaining wall.
The usual questions from the members that are asked ad nausium at each
meeting
were asked. The usual arguments ensued until those members were up to
speed
on the current status of the beach road. (This is a synopsis of this
portion
of the tape.)
Steve Ramsey homeowner and foreman on this project talked about the
missing
compaction tests on road and banks by Clark Land. Mr. Ramsey stated
that
he believed the retention wall was needed and at the time it was done.
The
rockery is basic to the Olympic Peninsula. Mr. Ramsey stated that he
has
met many homeowners and found dissension among them. His personal
feeling
is that we have a plan, let’s stick to it, and finish this project.
Let’s
take a sensible approach and quit the bickering and name-calling. It
seems
to him that every time one goes down to the road there is a new
surprise.
He wishes we could have had a better engineer, but states that we got
what
we paid for. Mr. Ramsey has confidence in the contractor. He says he is
doing
the best he can with what he has to work with. It was discussed and he
remembers
Mr. Stauffer being a part of this discussion, the turn-out needed to be
narrower
or retaining walls would have to go up on both sides. The road is not
level
with a 2% crown. So it has to be built up – the contractor is using
quarry
rocks to work on that. It is easier to do now while he is going down
the
road. It will cost more if done later. Mr. Ramsey says that we have
been
dealt a hand, so let’s play the hand and try to get the best results
possible.
Mr. Ramsey is resigning as of today for personal reasons.
More questions from members are shouted out with Mr. Stauffer talking
in
the background and agreeing with arguments about their suspicions.
Mr. Stauffer reiterated his suspicions and points at details from
contract
with contractor. The question regarding the crown is whether it is 2%
or
whatever. Mr. Ramsey pointed out that some additional materials may be
needed
– the road has proven to be a challenge even without the gnashing of
teeth
(arguments). He urges us again to get along and get the project
completed.
H.L. Font stated his opinion that the problem lies with the contractor.
Mr.
Ramsey stated that we could go back further to the engineer and the
problems
he did not address. Mr. Mrachovich stated that we are NOT asking for
more
money. The wall is budgeted in the contract, and was put in before it
had
been planned. There are ways to handle the issue.
Brenda Newman expressed her opinion that the BRC is lying and that they
are
all going to Hawaii with the SAPOA funds or something. Nancy Drake
expressed
her dismay by pointing out personality flaws between the Board and BRC
that
are hindering the flow of the project.
Barry Olson stated that he has 25 years of contract experience. He asks
for
members to submit their contract opinions in writing. Mr. Stauffer
brought
out AGAIN that the wall was okayed by a BRC member. This item was
previously
discussed at another Board Meeting and tabled.
Mr. Taney states that we are $6,000 short for contract payment. The
retention
wall was done on the contractor’s dime. The contract says that he is to
complete
the job in 60 days.
Karen Brandmeir called the BRC liars and left.
Sam Mrakovich tried over and over again to talk about how to pay for
the
wall. Larry Werner told about the engineer’s failure to address the
retaining
wall. The project is progressing in right order, and perhaps not to the
liking
of those who are of the adverse opinion. We are learning as we go along
because
it is not a nice clean job. Therefore, in spite of being called names,
the
BRC trudges on in order to complete the project. Larry Werner shares
that
he has pictures that show the necessity of retaining wall and more
surprises.
The pictures show the wet clay (with Mr. Stauffer’s shoe in the
picture).
The project will help dry out the clay. Mr. Stauffer said he would
agree
with us, if, if, if. Nancy Drake asks, “Who approved the engineer’s
plan?”
Mr. Taney agrees with Mr. Stauffer that services over $100 must be
approved
by the Board. The point is made that the BRC did not just spring up
from
nowhere. The BRC was created with Board approval last August.
Sam Mrakovich states that the BRC has been working against time. The
handout
of Beach Road Committee, page 2 is a viable plan. (Please see above.)
The
contractor has offered to finance at 7.25%, until next fall. Applause.
Mr. Stauffer’s solution is to let contractor “eat” the cost of the
wall.
Bill Andrew talked about a point of order that a motion cannot be
gained
because the entire membership was not property notified of the January
22,
2005 meeting today. Discussion of by-laws protocol is reiterated by Mr.
Taney
after the fact.
Barry Olson suggests that a portion of job be dropped to pay for
retention
wall. Mr. Stauffer did not like that idea, but offered no solution.
Elimination of problem may be to ask people to pay ahead.
The contractor declined to come to meeting. Nancy Drake states that the
contractor
met Everett Stauffer at the road and said he will not deal with a
five-year-old
attitude because he has a five-year-old at home to deal with.
Somebody thanked the BRC for volunteering and all their time!
Mr. Taney asked Barry Olson to take Steve Ramsey’s place. Mr. Olson is
to
report BRC findings and contractor progress to the Board.
Marydee Countryman stated that the wall needs to be paid for. The BRC
needs
to let the Board know of any expenditures.
Mr. Taney suggested that we pay for the materials and the contractor
pay
for the labor.
Larry Werner said it is not costing more money. The retention wall is
part
of the project.
Barry Olson suggested that we pick up at a later date. Mr. Olson knows
contractor
from another time. It is not in our interest to have him take the wall
out.
We got what we paid for in engineering.
Mr. Taney suggested a sit down meeting with contractor, Board, and BRC.
Someone suggested that the contractor should be asked to defer payment
until
we get the dues paid.
The surprise sewer line and retaining wall caused a shortfall this year.
A special membership meeting will be called.
Animal Control:
No one has called or written Mr. Taney regarding animal problems. The
name
and number of animal control is on website.
Dues:
Prepaid dues are encouraged. Operating expenses for 2006-7 will
increase
slightly.
SAPOA Board Vacancies – Kathleen DeStefano is working. We need a new
secretary.
Someone is needed to at least type the minutes. The secretary does not
have
to be an elected Board member.
A prepayment notice will be included in the next mailing to membership.
Put
year you are paying for on check.
C.E.R.T.(Community Emergency Response Team):
Marydee Countryman said that volunteer citizens trained for 15-20
hours,
are ready for disasters, and can be deployed to fire station and
community.
“Help” signs were handed out for putting in window. Nancy Drake asked
if
these signs can be used during power outages? Yes, power outage is a
disaster
to some people especially the elderly.
It is important to identity those who are handicapped and keep a watch
for
them.
More classes are coming in the spring. It is basic and you do not have
to
be a fireman. How to approach an emergency situation safely is taught
and
how to help your neighbors. Please consider joining.
We have 5 firefighters now. Applause. Wendy Abbot was acknowledged and
Bob
Meyer. Nancy Drake was thanked for her services over the years as she
has
retired.
The siren will be installed soon. Hopefully, it will be within a month
or
month-and-a-half. It is loud enough.
John Moore ham radio chief will be monitoring citizens (CB9) 24 hours a
day.
65 ham radio operators are available throughout the county. Have a
$10,000
grant to set up around county. Applause.
NOAA radio is VHF and tells of local problems like floods, etc. You can
buy
one at the County emergency office.
Should a disaster occur, one could check at the fire station to
find
out evacuation orders.
John Moore said that a ham radio station is set up at the fire station.
Neil Eckerson told of jack lighting going on where someone is using a
flashlight
to hunt at night. Please report any unknown car parked along the road,
especially
if you see someone flashing a light in the woods.
Mr. Taney thanked Neil Eckerson for working with Hugh of Diamond Point
with
the reader board. Applause.
6 and 7 Covenants
Platt 6 and 7 covenants have a tree planting issue. They must be
shorter
in order to preserve views. For redress you must go through the
Architectural
committee, who apprises the Board, who writes a letter to owners. There
is
no enforcement by Board. If this does not suffice, the homeowner must
find
legal satisfaction.
Nancy Drake asked about a home at 82 Hemlock Way, which is in violation
of
covenants. Mr. Taney asked for a memo from Nancy Drake stating the
problems
and Mr. Taney will write to homeowner.
New Business
Mr. Taney brought up the fact that running a business from your home is
addressed
by most covenants. People coming to the home and running a retail
business
is not allowed. Accepting advertising on the website and newsletter is
a
form of endorsement. It is the general consensus of the group that it
not
be done.
Larry Werner told the group that there was an attempted break in at the
contractor’s
trailer. The sheriff said that he found cowboy boot prints around the
trailer.
Please be aware and know that he may be after your stuff. The truck is
a
white Ford diesel pick up truck with dual wheels. Mr. Stauffer said
that
the truck matches the description of the truck that was thought to have
picked
up some siding from a Manzanita address.
Larry Werner supported what Mr. Mrakovich. said today. As a part of the
Beach
Road Committee, they have been called liars. He said that he does not
take
kindly to that and that it is flat out not true. Thank you.
Variance requests are never posted whether issues are passed or not.
The
protocol is to discuss with your Architectural Representative first. If
there
is a chance that it will pass, Vicki Taney will provide a list of
property
owners in that Plat, plus two sets of labels for the property owner to
create
and mail their own letter in their own words. Once the property owner
receives
the answer to his letter back he/she takes it to the AR. If a certain
percentage
passed, according to the Platt number, the AR takes it down to the
County
auditor for recording. Platt 6 and 7 is rapidly developing and the # of
variances
is an exception.
Platt 1 needs an AR.
Open Discussion
Bill Andrew discussed the by-laws, which he had addressed to the Board
by
letter with no response, and especially Article 6, which states the
term
Board members serve and is up for interpretation according to Mr.
Stauffer.
Bill said that the Officers can serve one year and another year
consecutively.
Mr. Stauffer gives his version again, stating that the Board members
can
serve up to 6 years. Bill asks that the by-laws be reviewed.
Mary D. Countryman said that revision of by-laws by committee is
overdue.
They should review all, not do it piecemeal. Therefore, the question
about
Bill’s version of by-law specifically Article 6 can be included.
Nancy Drake brought up the fact that a election nomination committee
has
not been used. Mr. Stauffer said that the Board has been remiss and may
be
remiss again if no one volunteers. Bill said Article 6, Section 7
covers
the nomination committee question.
A corner lot with entrances on both streets must have one front
setback.
Mr. Stauffer argues that some are done so and some are not.
Nancy Drake brings up a question whether the Board is making
Architectural
Representation decisions, which Mr. Stauffer admits is not what the
Board
should do. She has a letter from Mr. Taney that states the Board
authorized
three houses moved. Mr. Stauffer said that he was unclear about such a
letter.
Lew Morello moved to adjourn. The motion was seconded and passed
Respectfully submitted by,
Cecilia Eckerson